Cinnotek

All case studies

Plug-and-play capsule units at HKUST

Habitek delivered and installed two factory-built capsule units near HKUST’s New Academic Building on 29 August 2026, under the project direction of Professor Julian Lee.

A wrapped, factory-built capsule being crane-lifted as one module within the HKUST campus
A capsule lifted as one substantially complete module at HKUST. Photograph from Habitek’s final professional review.
Delivered
2 capsule units
Installed
29 August 2026
Location
HKUST, Hong Kong
Project Director
Professor Julian Lee

Factory-built. Installed on campus.

The pilot put the plug-and-play approach into practice: complete the main fabrication, internal fit-out and integrated systems off site, then focus campus works on delivery, lifting, positioning and final connections.

The final review records installation on 29 August 2026, ahead of the contractual completion date of 31 August. The project demonstrates modular delivery within a constrained, operational university campus.

From planning to handover

The project brought together design and interface review, deployment planning, transport and crane logistics, factory checks and operational handover. Professor Julian Lee provided project direction through this process.

The testing and handover record describes factory functional checks before dispatch, followed by site checks of transport condition, final interfaces and operational readiness.

Delivery, positioning and factory preparation

Two wrapped capsule units at the designated HKUST campus location
Two capsules at the receiving location
Two substantially complete capsule units positioned within the designated HKUST campus area.
Mobile crane and delivery vehicles beside existing HKUST campus buildings
Campus delivery and crane logistics
The access route and mobile-crane operation used to deploy the modules.
A wrapped capsule being positioned within the prepared HKUST receiving area
Positioning the capsule
A substantially complete module moved into the prepared receiving arrangement.
Finished capsule interior and ceiling light shown during a factory inspection
Interior prepared before dispatch
A factory inspection still reproduced in the testing and handover record.

Project photographs are extracted from Habitek’s final professional review and testing, commissioning and handover records.

The capsule-unit concept

The Habitek presentation illustrates how a self-contained modular space could support different campus activities. This product visual is separate from the actual HKUST installation photographs above.

Capsule product visual from Habitek’s project presentation, showing a glazed modular unit
Product illustration from Habitek’s project presentation.