Plug-and-play capsule units at HKUST
Habitek delivered and installed two factory-built capsule units near HKUST’s New Academic Building on 29 August 2026, under the project direction of Professor Julian Lee.

- Delivered
- 2 capsule units
- Installed
- 29 August 2026
- Location
- HKUST, Hong Kong
- Project Director
- Professor Julian Lee
Factory-built. Installed on campus.
The pilot put the plug-and-play approach into practice: complete the main fabrication, internal fit-out and integrated systems off site, then focus campus works on delivery, lifting, positioning and final connections.
The final review records installation on 29 August 2026, ahead of the contractual completion date of 31 August. The project demonstrates modular delivery within a constrained, operational university campus.
From planning to handover
The project brought together design and interface review, deployment planning, transport and crane logistics, factory checks and operational handover. Professor Julian Lee provided project direction through this process.
The testing and handover record describes factory functional checks before dispatch, followed by site checks of transport condition, final interfaces and operational readiness.
Delivery, positioning and factory preparation

Two substantially complete capsule units positioned within the designated HKUST campus area.

The access route and mobile-crane operation used to deploy the modules.

A substantially complete module moved into the prepared receiving arrangement.

A factory inspection still reproduced in the testing and handover record.
Project photographs are extracted from Habitek’s final professional review and testing, commissioning and handover records.
The capsule-unit concept
The Habitek presentation illustrates how a self-contained modular space could support different campus activities. This product visual is separate from the actual HKUST installation photographs above.